Timeline.

HISTORY OF OUR JOURNEY ON BUILDING OUR DREAM HOME - THE COLUMBUS 26.

28/07/12  Paid $300 deposit on land for reservation to the developer - Landcom at the Sales Office. (Land was only registered a week ago).
29/07/12  Paid $1000 initial deposit to GK of Wisdom Homes at their Display Home Sales Office.
31/08/12  Tender presentation and signing of tender at Wisdom Homes head office at Narellan.
14/09/12  Exchange of contract on the land with Landcom.
21/09/12  Architectural house plans received and no changes required.
28/09/12  Building contract was signed.
04/10/12  Introduction to our CSO of Wisdom Homes via email.
08/10/12  Colour selection appointment at Homeworld V-Wisdom Homes Display Village at Kellyville.
10 /10/12  Landscaping appointment at Wisdom Landscapes - Head Office. 
11/10/12  Landscaping plan received from Wisdom Landscape.
17/10/12  Landcom - Developer approval received.
19/10/12  Kitchen appointment with Timpelle Kitchens located at Prestons.
06/11/12  DA lodgement to Council.
09/11/12  Land settled after the settlement date crash three times, the original date was 29th October 2012.
12/11/12  Kitchen plan received from Timpelle Kitchens.
30/11/12  Tiles and Carpet appointment at Di Lorenzo Tiles  located at Bella Vista.
05/12/12  Electrical consultation appointment with Clipsal at Macquarie Park.
07/12/12  Landscaping quote received from Wisdom Landscapes.
18/12/12  DA Approve!
14/01/13  Preliminary variation received.
23/01/13 Construction Certificate received from SBAC.
05/02/13  Final Documents and Construction Plans received for review and sign off.
06/02/13  Our file is now with Production Estimating.
11/02/13  Builder's Signage erected.
12/02/13  Portaloo setup.
20/02/13  Site Fencing.
15/03/13  Site Cut / Excavation.
18/03/13  Piering.
19/03/13  Plumbing works before pouring the slab.
20/03/13  Formwork.
23/03/13  Slab.
11/04/13  Framing.
30/04/13  Bricking.
14/05/13  Roofing.
08/07/13  Gyprocking.
12/07/13 Cornice.
22/07/13  Stairs.
24/07/13  LOCKUP.
29/07/13 Architraves and Skirtings.
05/08/13 Waterproofing.
06/08/13 Kitchen cupboards installed and Painters started.
07/08/13 Bathroom,Ensuite and Powder room cabinets and basins installed.
09/08/13 Tilers started.
14/08/13 Electricals completed.
07/09/13 Ceasarstone Benchtops and other Internal fitouts.
09/09/13 Termite Reticulation System.
11/09/13 Kitchen Splashback and other Internal fitouts.
12/09/13 Landscaping Works started.
13/09/13 PCI,Wire shelvings,Driveway/Steps/Concrete path completed.
14/09/13 Carpets.
23/09/13 Final Internal and External Painting.
02/10/13 Soft & Hard Landscaping completed.
03/10/13 House clean.
08/10/13 Settlement-Handover.