Friday, 9 August 2013

Internal Photos - Part 1 +

All the scaffolding on the lower roofs were taken down. More photos of internal works done - Painting, Tiling and Cabinets in the Kitchen, Laundry, Powder room, Bathroom and Ensuite.























































Tuesday, 6 August 2013

Kitchen cabinets/bench + Painting + More Electrical Fit outs.

Kitchen bench and cabinets installed and Painting started plus more Electrical fit outs started today.








Friday, 2 August 2013

Electrical / Air-conditioning Cut outs for fit out & Partial Site clean up.

There were deliveries of mortar/sand yesterday and tiles for the ground floor and wet areas today plus partial external cleanup of building rubbish materials and Electrical / Air-conditioning Cut outs for fit out later on.